Today I spent in Sacramento (yes, it was close to 100 degrees) with the commissioners of the CEC who presided over the Efficiency Committee Load Management Standards Workshop on Enabling Technologies.
The meeting was overtly to talk about "Demand Response" technologies -- that is, technologies that can temporarily reduce commercial, industrial and/or residential power loads during critical periods of the day (especially during the summer). This is important to "level-out" the demand placed on the electrical grid - and avoid having to over-build generation/transmission capabilities.
Why was this so interesting? three reasons....
One was that it was a great opportunity to hear what officials from the California Public Utilities Commission (CPUC), the California Independent System Operator (California ISO), Lawrence Berkeley Labs, PG&E, Southern California Edison, San Diego Gas & Electric, and Sacramental Muni had to say about technologies they're considering.
Two was the opportunity to see a number of vendors (Cassatt Included) present and demonstrate some cool ideas for curbing industrial and residential loads - - smart/programmable thermostats etc., Not to mention the various wired, satellite, Wimax, FM, and other really innovative ways for signaling "events" to these devices over wide areas (think: States).
Three (and most interesting to this author) was that the majority of "new" technologies were focused on the residential market -- smart thermostats and the like. To my surprise, essentially none of the technologies addressed the 60 gigawatthours of energy being consumed by data centers or ways to either permanently curb this number, or at least to curtail it during "demand response" events.
I'll be following-up with attendees, including officials from the major California utilities (who drive their Demand Response programs) to see how we can help reduce the energy consumption and wasted power in large data centers.
Thursday, June 19, 2008
Monday, June 9, 2008
Rate your data center efficiency ! !
Two very noteworthy announcements in the past few weeks for those concerned with diagnosing how energy efficient their data centers are. And (surprisingly) these announcement & tools are coming from the US government who, in my opinion, is out in front of industry for the first time.
First, the US DOE is now beta-testing it's "DC-Pro" (Data Center Profiling) tool as part of it's "Save Energy Now" program. The tool is in its beta-testing stage, and is currently available here, with a really complete FAQ available as well. This tool is great in that it asks for tons of information (an education in-and-of itself), yields an anonymous ranking of your data center relative to peers, and also makes suggestions as to where else you can seek additional efficiencies in your environment.
Second, and in conjunction with the DOE, The US EPA is piloting its Energy Star rating for data centers, much the way they have Energy Star ratings for buildings/structures. The EPA is extending initial participants in the study to July 1, 2008. Information, expression-of-interest forms, etc. are available on the EPA Enterprise Server and Data Center Efficiency Page. Cassatt, among others, will be part of this study -- which also ranks efficiencies of data centers and awards the Energy Star label to the top quartile of annual participants. Note that this is less a diagnostic tool (as-is the DOE DC-Pro tool) and more of a recognition of performance.
My suggestion is to participate in both... If for no other reason than it will *cause* your organization to begin to ask questions, take measurements, and begin to learn tactical/tangible sources of efficiency improvements -- rather than simply discuss abstract concepts.
First, the US DOE is now beta-testing it's "DC-Pro" (Data Center Profiling) tool as part of it's "Save Energy Now" program. The tool is in its beta-testing stage, and is currently available here, with a really complete FAQ available as well. This tool is great in that it asks for tons of information (an education in-and-of itself), yields an anonymous ranking of your data center relative to peers, and also makes suggestions as to where else you can seek additional efficiencies in your environment.
Second, and in conjunction with the DOE, The US EPA is piloting its Energy Star rating for data centers, much the way they have Energy Star ratings for buildings/structures. The EPA is extending initial participants in the study to July 1, 2008. Information, expression-of-interest forms, etc. are available on the EPA Enterprise Server and Data Center Efficiency Page. Cassatt, among others, will be part of this study -- which also ranks efficiencies of data centers and awards the Energy Star label to the top quartile of annual participants. Note that this is less a diagnostic tool (as-is the DOE DC-Pro tool) and more of a recognition of performance.
My suggestion is to participate in both... If for no other reason than it will *cause* your organization to begin to ask questions, take measurements, and begin to learn tactical/tangible sources of efficiency improvements -- rather than simply discuss abstract concepts.
Friday, June 6, 2008
Real-life data center efficiency projects!
It's about time the industry stopped talking about data center & IT energy efficiency, and started doing something.
The good news is the first wave of actual projects, metrics and results is about to be unveiled. The Silicon Valley Leadership Group (SVLG) is hosting their first Data Center Summit '08 in Santa Clara CA on June 26. The 1-day event will be co-sponsored by the California Energy Commission, the US DOE, and Lawrence Berkeley National Labs.
The summit will have 11 case studies of actual projects - each co-sponsored by the SVLG, but implemented by one or more silicon valley companies & technology vendors. Each project addresses a different aspect of data center energy efficiency - from power management to cooling improvements to server efficiency increases. The point being how we can show real progress, and share the data with others. I believe that California's own CIO will be attending, various other officials, and possibly folks from the EPA as well.
Cassatt, I might add, will be co-presenting a real-life energy-saving project with a user of our Active Power Management technology.
Registration is a mere $295 - you can go to the SVLG website and sign up yourself.
The good news is the first wave of actual projects, metrics and results is about to be unveiled. The Silicon Valley Leadership Group (SVLG) is hosting their first Data Center Summit '08 in Santa Clara CA on June 26. The 1-day event will be co-sponsored by the California Energy Commission, the US DOE, and Lawrence Berkeley National Labs.
The summit will have 11 case studies of actual projects - each co-sponsored by the SVLG, but implemented by one or more silicon valley companies & technology vendors. Each project addresses a different aspect of data center energy efficiency - from power management to cooling improvements to server efficiency increases. The point being how we can show real progress, and share the data with others. I believe that California's own CIO will be attending, various other officials, and possibly folks from the EPA as well.
Cassatt, I might add, will be co-presenting a real-life energy-saving project with a user of our Active Power Management technology.
Registration is a mere $295 - you can go to the SVLG website and sign up yourself.
Thursday, June 5, 2008
Why IT monitoring is costing the industry money
I was giving a presentation to an analyst today, describing how an optimized IT infrastructure is inherently energy efficient.
And then it occurred to me: The entire IT monitoring and reporting sector (those guys who write software that pages you when something goes wrong in your data center) is perpetuating waste.
The software assumes that there's a problem only when service level agreements (SLAs) are too low -- but never when they are too high. This implies that alert storms get triggered when you're under-provisioned. But when you're over-provisioned, it's bad too... too much capital being wasted delivering an SLA that's better than needed. This scenario is probably replayed during every off-peak hour a data center operates.
What you don't measure, you can't manage. And therein lies the waste being perpetuated by IT: it's been implicitly assumed that too much infrastructure is OK.
Actually, what we need is a monitoring and control system that maintains an optimal service level -- not too high, not too low. And, when demand changes, automatically adjusts resources to re-optimize the SLAs. That adjustment might include re-allocating or de-allocating hardware, or re-provisioning servers on-the-fly.
Just once, I'd like one of my IT friends to get an alarm delivered to his pager that reads "system critically over-provisioned: wasting power"
And then it occurred to me: The entire IT monitoring and reporting sector (those guys who write software that pages you when something goes wrong in your data center) is perpetuating waste.
The software assumes that there's a problem only when service level agreements (SLAs) are too low -- but never when they are too high. This implies that alert storms get triggered when you're under-provisioned. But when you're over-provisioned, it's bad too... too much capital being wasted delivering an SLA that's better than needed. This scenario is probably replayed during every off-peak hour a data center operates.
What you don't measure, you can't manage. And therein lies the waste being perpetuated by IT: it's been implicitly assumed that too much infrastructure is OK.Actually, what we need is a monitoring and control system that maintains an optimal service level -- not too high, not too low. And, when demand changes, automatically adjusts resources to re-optimize the SLAs. That adjustment might include re-allocating or de-allocating hardware, or re-provisioning servers on-the-fly.
Just once, I'd like one of my IT friends to get an alarm delivered to his pager that reads "system critically over-provisioned: wasting power"
Friday, May 30, 2008
More support for server power management
It was a great week for those endorsing the concept of actively-managing the power status of servers to drastically reduce data center power consumption.
First, Andy Lawrence with The 451 group outlined it as
1) Enterprise Desktop power management
2) Datacenter/server power management
3) Integrated datacenter power distribution management
Bridget Botelho in SearchDatacenter.com also managed to speak with a user of Cassatt's active response. The company began with a small environment of about eight devices, mostly servers. Once the use of Active Power Management was validated, the company increased to 40 devices, and now successfully runs Active Power Management on about 120 devices.
First, Andy Lawrence with The 451 group outlined it as
... a technology that optimizes the energy efficiency of computers and other electronic devices by reducing power consumption to the lowest possible point while still supporting minimal agreed business or functional objectives. It does this by placing equipment or components into reduced power states according to policies and schedules or in response to a drop in machine utilization. It can also restore equipment to a fully functioning mode according to the same principles.In one of his recent works, "Power management: a three-phased, multispeed market" that there are 3 waves of power management:
1) Enterprise Desktop power management
2) Datacenter/server power management
3) Integrated datacenter power distribution management
"Although this is a market in its infancy, [server] power management will be an important, if not critical, piece of the technological jigsaw, we believe, and one that needs to be in place to run an eco-efficient datacenter. Cassatt is one of a handful of companies making the early running. Cassatt Active Response 5.1 adds a critical on-demand capability that improves the business case for the technology.
Bridget Botelho in SearchDatacenter.com also managed to speak with a user of Cassatt's active response. The company began with a small environment of about eight devices, mostly servers. Once the use of Active Power Management was validated, the company increased to 40 devices, and now successfully runs Active Power Management on about 120 devices. The global company has 5,000 racks of servers, most of them in Sunnyvale, Calif., and others located around the world. Prior to using Cassatt, the company had no way to manage system power, but the high cost of power in California and a sense of corporate responsibility prompted it to try Cassatt's software.
I really like the way the user (who shall remain nameless) endorses the concept (at right)
Wednesday, May 21, 2008
IT Automation & Power Mangement: a Synopsis of Recent Coverage
This week has seen an unusual share of coverage about IT energy issues - from a lot of different angles. However, whether or not "green" was stuck to the heading, everyone seems to agree that energy is a serious operational cost issue, and the bottom line for any energy-related initiative is always cost.
Grids & Power Management: Howard Marks of InformationWeek writes of his observation that in storage, MAID (Massive Arrays of Inactive Disks) regularly shuts down idle drives. And in grid arrays he's now seeing RAIN (Redundant Arrays of Independent Nodes) with a similar model -- essentially shutting down servers when not in use.
IT Energy Survey: Erin Bell of eChannelLine referenced a recent survey done by Cassatt regarding the degree of energy waste in data centers, and operators' willingness to look at power management as one option to curb it.
Automation = Efficiency: Gail Dutton in Virtual Strategy Magazine writes of the myth and realities of running a true "lights-out" data center, how automation plays a supporting role, and how various levels of efficiencies can be recovered by doing so... if management is willing to cede control.
Automation & Utility Computing: John Rath in the Data Center Links blog posted some humorous/insightful comments about the current reality of Utility Computing: "Myth? I don't think so. I think it is the early stages, but definitely not a myth.. I don't think utility computing, cloud computing, grid computing -- what ever you want to call it is a myth. Far from it. The applications of these technologies will be seen in different places, for different reasons and at different paces over the coming years." I couldn't agree with you more, John.
Curbing the Electric Consumption of Avatars: My buddy Dave Ohara on the Green Data Center Blog reminds us of Nicholas Carr's observation that the power consumption of a Second Life avatar is about that of a real-life Brazilian. Sort of tongue-in-cheek, but getting at the point that these computing environments numbering 1,000's of servers also need to be power-controlled during off-peak periods.
And finally,
It's about Efficient Operation, stupid: Arthur Cole of Data Center Central -- bless his heart -- finally implies the observation we've been pointing out for months: it's great to pursue efficient equipment to achieve IT energy efficiency, but to get the rest of the way, you need to pursue Efficient Operation of the equipment, too.
Grids & Power Management: Howard Marks of InformationWeek writes of his observation that in storage, MAID (Massive Arrays of Inactive Disks) regularly shuts down idle drives. And in grid arrays he's now seeing RAIN (Redundant Arrays of Independent Nodes) with a similar model -- essentially shutting down servers when not in use.
IT Energy Survey: Erin Bell of eChannelLine referenced a recent survey done by Cassatt regarding the degree of energy waste in data centers, and operators' willingness to look at power management as one option to curb it.
Automation = Efficiency: Gail Dutton in Virtual Strategy Magazine writes of the myth and realities of running a true "lights-out" data center, how automation plays a supporting role, and how various levels of efficiencies can be recovered by doing so... if management is willing to cede control.
Automation & Utility Computing: John Rath in the Data Center Links blog posted some humorous/insightful comments about the current reality of Utility Computing: "Myth? I don't think so. I think it is the early stages, but definitely not a myth.. I don't think utility computing, cloud computing, grid computing -- what ever you want to call it is a myth. Far from it. The applications of these technologies will be seen in different places, for different reasons and at different paces over the coming years." I couldn't agree with you more, John.
Curbing the Electric Consumption of Avatars: My buddy Dave Ohara on the Green Data Center Blog reminds us of Nicholas Carr's observation that the power consumption of a Second Life avatar is about that of a real-life Brazilian. Sort of tongue-in-cheek, but getting at the point that these computing environments numbering 1,000's of servers also need to be power-controlled during off-peak periods.
And finally,
It's about Efficient Operation, stupid: Arthur Cole of Data Center Central -- bless his heart -- finally implies the observation we've been pointing out for months: it's great to pursue efficient equipment to achieve IT energy efficiency, but to get the rest of the way, you need to pursue Efficient Operation of the equipment, too.
Monday, May 19, 2008
A big step forward for self-managing data centers
Today there is a modest but hugely-meaningful announcement regarding data center operational efficiency coming out of Cassatt here in San Jose. It's about Cassatt Active Response 5.1 software, and it includes the ability to take actions on infrastructure based on application demand. That means that server power control, or even entire server repurposing and network provisioning, can be triggered by the demand (or service level) of a given application.
This means that if you run a development lab, idled machines might be automatically power-down after a period of time (say, after a test run) to save power. It means that a server farm can automatically trigger provisioning additional servers if service levels drop below a pre-determined threshold - saving time. It means as different application demands ebb and flow, the data center will adapt to demand by re-purposing (or retiring) bare-metal hardware -- making the best use of capital. And all of this whether-or-not virtualization is present, regardless of the underlying platform, and without adding software layers.
You'll find this concept filed under Gartner's Real-Time Infrastructure (RTI) category, under Forrester's Organic IT concept, or sometimes under Utility Computing. You've even seen big vendors predicting it as a vision. But I'm happy to point out that we're doing some of it already today. Think of this as another step toward a greener data center, because it really optimizes all forms of operational and capital efficiency...
The simplest application of this Demand-Based Policy Management is with Active Power Management of data center servers to curb rampant power waste. (Check out Who's Recommending Power Management) The concept has been long-used on desktops (check out 1E or Verdiem; there are over a half-million desktops under power management today). In IT environments such as dev/test, we've seen opportunities to cut gross power consumption by 30% or more in a few months. All this by simply monitoring the server activity and then gracefully shutting-down idled hardware (where idleness can be defined any way data center managers prefer). Check out the endorsements of power management from the EPA's Andrew Fanara as well as from Jon Koomey in the Cassatt press release. You can also watch a webcast about Active Power Management
A more sophisticated use of demand-based policy is to automatically maintain the service-level of applications. Take the server farm example... or for that matter, a SOA service. In either example, demand on the service may be cyclical or unpredicatable. Instead of massively over-provisioning hardware, one could use a service level metric (again, of your determination) to provide control. If service level drops (say, due to increased demand, or perhaps because of equipment failure) the Cassatt system will simply power-up or re-purpose another piece of hardware and create a new server to increase compute capacity. And you don' t need a virtualization platform to do this. (Or you could. Previously we announced compatibility with VMware ESX as well as with Xen.) Check out the 10 min webcast on demand-based policy management.
The benefits here are massive: Besides the power saved when not using a piece of equipment, you're maximizing the use of capital because it's dynamically repurposed. Similar control is used for Cloud Computing infrastructure like Amazon Web Services (AWS) and they've achieved a compute price-point unheard-of in the industry: $0.10 per CPU per hour. Try that with your existing infrastructure.
My, my. I've overlooked the remainder of the Cassatt announcement:
This means that if you run a development lab, idled machines might be automatically power-down after a period of time (say, after a test run) to save power. It means that a server farm can automatically trigger provisioning additional servers if service levels drop below a pre-determined threshold - saving time. It means as different application demands ebb and flow, the data center will adapt to demand by re-purposing (or retiring) bare-metal hardware -- making the best use of capital. And all of this whether-or-not virtualization is present, regardless of the underlying platform, and without adding software layers.
You'll find this concept filed under Gartner's Real-Time Infrastructure (RTI) category, under Forrester's Organic IT concept, or sometimes under Utility Computing. You've even seen big vendors predicting it as a vision. But I'm happy to point out that we're doing some of it already today. Think of this as another step toward a greener data center, because it really optimizes all forms of operational and capital efficiency...
The simplest application of this Demand-Based Policy Management is with Active Power Management of data center servers to curb rampant power waste. (Check out Who's Recommending Power Management) The concept has been long-used on desktops (check out 1E or Verdiem; there are over a half-million desktops under power management today). In IT environments such as dev/test, we've seen opportunities to cut gross power consumption by 30% or more in a few months. All this by simply monitoring the server activity and then gracefully shutting-down idled hardware (where idleness can be defined any way data center managers prefer). Check out the endorsements of power management from the EPA's Andrew Fanara as well as from Jon Koomey in the Cassatt press release. You can also watch a webcast about Active Power Management
A more sophisticated use of demand-based policy is to automatically maintain the service-level of applications. Take the server farm example... or for that matter, a SOA service. In either example, demand on the service may be cyclical or unpredicatable. Instead of massively over-provisioning hardware, one could use a service level metric (again, of your determination) to provide control. If service level drops (say, due to increased demand, or perhaps because of equipment failure) the Cassatt system will simply power-up or re-purpose another piece of hardware and create a new server to increase compute capacity. And you don' t need a virtualization platform to do this. (Or you could. Previously we announced compatibility with VMware ESX as well as with Xen.) Check out the 10 min webcast on demand-based policy management.
The benefits here are massive: Besides the power saved when not using a piece of equipment, you're maximizing the use of capital because it's dynamically repurposed. Similar control is used for Cloud Computing infrastructure like Amazon Web Services (AWS) and they've achieved a compute price-point unheard-of in the industry: $0.10 per CPU per hour. Try that with your existing infrastructure.
My, my. I've overlooked the remainder of the Cassatt announcement:
- a new interface to interact with external systems - either management systems, or equipment like Load Balancers. Take the example of using an F5 load balancer in an environment with dynamic repurposing. As new servers are provisioned, Active Response can communicate in real-time to the balancer and provide the new VIPs in seconds as the servers are brought online.
- a new set of platform compatibilities, including power distribution units, used to remotely power-manage servers. This is in addition to a massive list of supported hardware, OSs, applications and VM technologies. This solution will work with what you have today :)
Labels:
Green IT,
Power Management,
Utility Computing